Chapter 7 Assignment Problem and Sequencing
Open with Full Screen in HD Quality
Project on Assignment Problem and Sequencing
Assignment Problem
The Assignment Problem is a fundamental combinatorial optimization problem that deals with the allocation of resources to tasks. The goal is to determine the most efficient assignment of tasks to agents while minimizing the total cost or maximizing the total profit. Here's a detailed explanation:
Definition: The assignment problem involves a set of agents and tasks. Each agent is to be assigned to one task, and each task is to be assigned to one agent. There is a cost associated with each assignment, and the objective is to find the assignment that minimizes the total cost.
Cost Matrix: The problem is typically represented by a cost matrix , where represents the cost of assigning agent to task .
Objective: The objective is to find a permutation of the set that minimizes the total cost:
Solution Methods:
- Hungarian Algorithm: This is a combinatorial optimization algorithm that solves the assignment problem in polynomial time.
- Linear Programming: The assignment problem can also be formulated and solved as a special case of the linear programming problem.
Sequencing Problem
Sequencing problems involve determining the order in which a set of tasks or jobs should be performed to optimize a specific objective, such as minimizing total completion time, minimizing lateness, or maximizing machine utilization.
Definition: In sequencing problems, we have a set of jobs that need to be processed on one or more machines. Each job has a specific processing time and possibly other attributes such as due dates or priorities.
Types of Sequencing Problems:
- Single Machine Sequencing: Determining the optimal sequence of jobs on a single machine.
- Parallel Machine Sequencing: Jobs need to be scheduled on multiple machines.
- Flow Shop Sequencing: Jobs pass through multiple machines in the same order.
- Job Shop Sequencing: Jobs pass through multiple machines, but the order can vary for each job.
Objective Functions:
- Minimize Makespan: The makespan is the total time required to complete all jobs. The objective is to minimize the time when the last job finishes.
- Minimize Total Completion Time: The objective is to minimize the sum of the completion times of all jobs.
- Minimize Maximum Lateness: Lateness is the difference between the completion time of a job and its due date. The objective is to minimize the maximum lateness among all jobs.
- Minimize Total Tardiness: Tardiness is the amount of time a job finishes after its due date. The objective is to minimize the sum of the tardiness of all jobs.
Solution Methods:
- Exact Algorithms: These include dynamic programming, branch and bound, and integer programming methods that guarantee finding the optimal solution.
- Heuristic Algorithms: These include methods like the shortest processing time (SPT) rule, earliest due date (EDD) rule, and others that provide good solutions in a reasonable time but do not guarantee optimality.
- Metaheuristic Algorithms: These include genetic algorithms, simulated annealing, and tabu search, which are used for complex sequencing problems where traditional methods are not feasible.
Relationship Between Assignment and Sequencing Problems
While the assignment problem focuses on finding an optimal allocation of tasks to agents based on a cost matrix, sequencing problems focus on determining the optimal order of tasks to meet a specific objective. Both types of problems are pivotal in operations research and optimization, often applied in manufacturing, logistics, and scheduling scenarios.